EB-5 Construction at Harbourside Place
August 29, 2012 Crews are working at a fast pace to complete the demucking of the property at Harbourside Place. With nearly 75% complete, they will...
August 29, 2012 Crews are working at a fast pace to complete the demucking of the property at Harbourside Place. With nearly 75% complete, they will...
August 20, 2012 Progress at Harbourside Place has been abundant, as crews are nearly 75% done with demucking the property. These most recent aerial photos show...
August 13, 2012 Another week of work has been completed at Harbourside Place, where crews continue to make headway in completing the demucking process at the...
August 6, 2012 Another update at the Harbourside Place, EB-5 funded, construction project. Crews continue to work to demuck the property and prepare the sub-grade of...
August 5, 2012 According to the Association to Invest In the USA (IIUSA), a 501(c)(6) not-for-profit industry trade association of active EB-5 Regional Centers ("Regional Centers"),...
July 26, 2012 Crews continue to push on with construction at the Harbourside Place project. With a number of machines working dawn to dusk, the crews...
July 20, 2012 Here are the updated monthly aerial shots of the Harbourside Place, EB-5 Project. You can see that the crews have begun demucking the...
July 14, 2012 With permits in hand, the construction team at the Harbourside Place project have begun the tedious process of demucking the facility to make...
PRESS RELEASE – FOR IMMEDIATE RELEASE Palm Beach Gardens, Florida - March 28, 2012 The Town of Jupiter invites residents to the ribbon cutting ceremony for the...
March 21, 2012 The EB-5 Program is seeing a slowing of the approval of new regional centers across the United States. According to The Daily, nationwide,...